The highway project wrapped up in Phillips as of Friday, September 19, 2025.
On Monday, September 22, 2025, the sidewalks project will begin downtown on Lake Avenue.
According to Jim Heizler of the Department of Public Works, the first day of each phase will involve removing the old concrete, installing new water shut off stops, and setting the elevation. The next two days will be when the new concrete is installed. The sidewalks cannot be walked on for at least 24 hours after installation.
Phase 1 will include the west side of the street from Elm Street to Chestnut Street from September 22 through September 26.
Phase 2 will continue on the west side from Chestnut Street to Maple Street from September 29 to October 3.
(Article continues after promotional message)
For more details about the job, click this link.
On the east side, Phase 3 will begin on the south end and continue north stopping before the intersection of Cherry Street and is scheduled for October 6 to October 10.
The northern portion of the east side that remains is scheduled for October 13 through October 17.
Fall Harvest Fest is October 4, 2025, and all sidewalks will be open to the public on that day.
According to a building inspector, salt should not be used on new concrete sidewalks during the upcoming winter season. Salt can penetrate the concrete, which is still curing, and cause damage. Instead of salt, alternatives like sand or salt-free grit may be used for traction.